OngoingWork dey go onBoki LGARoad Construction
Boki East-West Road
17km laterite road under construction. First 3km asphalted through forest stretch, with graded shoulders and gravel edging.
Ongoing • 3 km of 17 km asphalted
AsphaltedCoal tar don enter3 of 17 km (18%)
SourceWhere e come from: Six drone and road-level photos, three before and three after, labelled “Boki EastWest”.
What the photos showWetin di pictures show
- Before: a red laterite track with deep wheel ruts and loose soil.
- After, on the finished 3 km: a continuous asphalt surface through dense forest.
- Graded shoulders on both sides, with gravel edging along the carriageway.
- The remaining 14 km is still laterite and has not yet been asphalted.
Evidence on recordProof wey we get
- Six drone and road-level photos, three before and three after, labelled “Boki EastWest”.
- Road length (17 km) and progress (3 km asphalted) from Evidence Group's field report.