CompletedE don finishOdukpani LGAElectrification
HT network and substation, Okurikang Junction
High-tension network and transformer substation at Okurikang Junction restored.
Completed • July 2025
SourceWhere e come from: Cross River State Electrification Agency (SEA), Performance Review 2026
What the photos showWetin di pictures show
- Substation rebuilt and signed: “Rehabilitated by Cross River State Electrification Agency”.
- Linemen restringing the network.
Evidence on recordProof wey we get
- Cross River State Electrification Agency (SEA), Performance Review 2026