Ask Evidence AI about this sectorProjects
Completed (date not stated)Electrification500 kVA substation, Summit Hills, Calabar · Calabar MunicipalA brand-new 500 kVA substation built at Summit Hills, Calabar, by the State Electrification Agency. New 500 kVA substation, built from the ground up. Fenced, painted and signed: “Constructed by C.R. State Electrification Agency, July 2025”.Documented by Evidence Group from official papers1 source
Completed (date not stated)ElectrificationHT network and substation, Ndok Junction to Idim Mbube, Ogoja · OgojaHigh-tension lines and the substation from Ndok Junction to Idim Mbube restored, bringing light back to Ogoja communities. Poles and high-tension lines restrung. Transformer substation rehabilitated.Documented by Evidence Group from official papers1 source
Completed (date not stated)Electrification500 kVA substation, House of Assembly Quarters, Ekorinim · Calabar MunicipalA vandalised 500 kVA transformer substation at the House of Assembly Quarters, Ekorinim, brought back to life. Vandalised 500 kVA (11/0.415 kV) substation rehabilitated.Documented by Evidence Group from official papers1 source
Completed (date not stated)ElectrificationAyikang to Gakem, Bekwarra · BekwarraPower restored from Ayikang to Gakem in Bekwarra with a new transformer installed. New transformer mounted and connected. Engineers commissioning the installation.Documented by Evidence Group from official papers1 source
Completed (date not stated)ElectrificationTransformer substation between Awi and Okom-Ita, Akamkpa · AkamkpaThe transformer substation between Awi and Okom-Ita in Akamkpa rehabilitated. Transformer substation repaired and reconnected.Documented by Evidence Group from official papers1 source
Completed (date not stated)ElectrificationReticulation, Adiabo Ikot Ukpa community · OdukpaniAdiabo Ikot Ukpa community wired up: new reticulation and a rehabilitated substation. Substation enclosure rebuilt and signed by SEA. New poles and lines across the community.Documented by Evidence Group from official papers1 source
Completed (date not stated)ElectrificationIkot-Okon Abasi, Odukpani · OdukpaniElectricity infrastructure at Ikot-Okon Abasi in Odukpani rehabilitated. Transformer rehabilitated inside a secured enclosure.Documented by Evidence Group from official papers1 source
Completed (date not stated)ElectrificationHT network and substation, Okurikang Junction · OdukpaniHigh-tension network and transformer substation at Okurikang Junction restored. Substation rebuilt and signed: “Rehabilitated by Cross River State Electrification Agency”. Linemen restringing the network.Documented by Evidence Group from official papers1 source
Completed (date not stated)ElectrificationHT lines and substations, Akpap Okoyong and Ikot Okon Effiong, Odukpani · OdukpaniPower lines and substations from Akpap Okoyong to Ikot Okon Effiong in Odukpani rehabilitated. Feeder pillar rewired. Transformers serviced and reconnected.Documented by Evidence Group from official papers1 source
Completed (date not stated)ElectrificationAkpap Okoyong to Okurikang Junction, Odukpani · OdukpaniThe line from Akpap Okoyong to Okurikang Junction rehabilitated. Transformer installation by SEA engineers in safety gear.Documented by Evidence Group from official papers1 source
Completed (date not stated)ElectrificationNew substation, Enyia Nfo community, Esuk Afu satellite town · CalabarA new 11/0.415 kV substation built for Enyia Nfo community in Esuk Afu satellite town. New substation with a protective cage and painted enclosure.Documented by Evidence Group from official papers1 source
Completed (date not stated)ElectrificationNde network, Ikom · IkomThe Nde electricity network in Ikom rehabilitated and a transformer reinstalled. Transformer installed and connected on site.Documented by Evidence Group from official papers1 source
Completed (date not stated)ElectrificationElectrification of Idim-Ita community, Calabar South · Calabar SouthIdim-Ita community in Calabar South electrified. Feeder pillar installed. New poles and lines strung into the community.Documented by Evidence Group from official papers1 source
Completed (date not stated)ElectrificationSubstation rehabilitation, Yahe, Yala · YalaThe Yahe substation in Yala rebuilt, secured and signed off. Substation enclosure rebuilt, with razor-wire security. Signed: “Constructed by Cross River State Electrification Agency”.Documented by Evidence Group from official papers1 source
Under constructionElectrification500 kVA transformer, Nsefik Layout, Nsefik/Atekong, Calabar · Calabar MunicipalA replacement 500 kVA transformer delivered to Nsefik Layout, Calabar. New transformer lifted into place.Documented by Evidence Group from official papers1 source
Under constructionElectrification500 kVA transformer, Okuku, Yala · YalaA new 500 kVA transformer delivered to Okuku in Yala, and the community came out to receive it. Transformer delivered to the site. Community members gathered at the handover.Documented by Evidence Group from official papers1 source
Under constructionElectrification1 MVA transformer, Ekorinim (by Redeemed Church) · Calabar MunicipalA bigger 1 MVA transformer being installed at Ekorinim to carry more homes and businesses. New 1 MVA transformers delivered. Installation under way.Documented by Evidence Group from official papers1 source
Under constructionElectrificationHome solar systems for rural communities · Cross River StateSolar systems being installed in homes across rural Cross River: lights and fans where the grid does not reach. A family reading under solar light at night. Installers setting up a solar-powered fan. Teams visiting rural homes.Documented by Evidence Group from official papers1 source